On April 12, 2026, Beston Group successfully completed the installation and commissioning of a BLJ-16 TDU project in Africa. Executed in just 42 days, this record-breaking deployment transforms hazardous oilfield waste into valuable industrial fuel, empowering the client to achieve rapid operational readiness and capture sustainable revenue from resource recovery.

Strategic Partnership: Local Resource Recovery & Dual-Revenue Business Model
In this project, the client operates in close collaboration with local oilfields in Africa, taking direct responsibility for the management and processing of oil sludge generated during extraction and production activities.
Objective 1: Capturing Waste Treatment Service Fees
The client generates immediate cash flow by providing professional, compliant disposal services for hazardous oil sludge, helping oilfields meet environmental requirements while securing a steady service-based income.
Objective 2: Maximizing Profit from Pyrolysis Oil Sales
Beyond simple disposal, the project focuses on resource recovery. The high-quality pyrolysis oil extracted from the sludge is sold as industrial fuel, allowing the client to capture significant market value from what was previously considered waste.


Record-Breaking Efficiency: 42-Day Rapid Installation and Commissioning
In response to the client’s operational needs, Beston Group implemented a high-efficiency deployment strategy. By completing the entire process from arrival to final commissioning in just 42 days, our technical team set a new internal speed record, allowing the client to transition toward production far ahead of schedule:
Project Information
- Equipment model: BLJ-16 Thermal Desorption Unit (TDU)
- Key components: Corrosion-resistant 304 stainless steel reactor and a high-efficiency screw feeder system
- Processing material: A mix of landing oil sludge and oil-based drill cuttings (OBM)
Project Key Timeline
- Installation period: March 2 – March 31, 2026
- Commissioning period: April 1 – April 10, 2026
- Project completion & acceptance period: April 11 – April 12, 2026
- Total duration: 42 Days (Setting a new benchmark for project delivery)


Project Conclusion: Ready for Full-Scale Operation
The installation and commissioning of the BLJ-16 oil sludge pyrolysis plant have been successfully completed, marking the transition to the pre-production phase. As the client currently moves forward with obtaining relevant operational certifications, the project is strategically positioned to realize its commercial objectives.